Copy Project Process
Use the Copy Project API process to create a new Cobra project by copying an existing project. You can also use this process to copy a Cobra master project which results in a new copy of the master project and all its children projects.
Process Settings
Below are the settings you must define for the Copy Project API process.
Setting | Description | Sample Value |
---|---|---|
ProcessID | This setting informs Cobra to run the copy Project process. | CopyProject |
CopyFrom | This setting refers to the name of the source project to copy
This setting is required. |
Demo |
CopyTo | This setting identifies the name of the new Cobra project to create.
This setting is required. |
Demo Advanced |
CopyData | This setting indicates whether data is copied from the source project into the new project. A value of
1 indicates that the data is copied.
This setting is optional, and the default value is 0. |
1 |
DeleteTarget | This setting indicates whether Cobra should delete the existing copy of the new project. A value of
1 informs Cobra to delete the existing copy of the new project.
This setting is optional, and the default value is 1. |
0 |
CopyCalendar | Use this setting to copy the calendar from the source project and rename it to the new name of the project..
A value of 1 informs Cobra to copy the calendar. A value of 0 informs Cobra to use the same calendar as the source project for the new project. This setting is optional, and the default value is 1. |
0 |
NewDescription | This setting refers to the description of the new Cobra project.
This setting is optional. |
This is demo project. |
Sample Script
Below is a sample script file for the Copy Project API process.
[Process018]
ProcessID=CopyProject
CopyFrom=Demo
CopyTo=Demo Advanced
CopyData=1
DeleteTarget=0
CopyCalendar=0
NewDescription=This is demo project.